TPJ Engineering Sdn Bhd - Bridge Construction Specialist

Gurney Wharf Marine Engineering Works

23 December 2024

Project

Overview

Water Body A Reclamation Works at Gurney Bay

Completed

TPJ Engineering completed the reclamation works for Water Body A, a 6.95-acre component of the Gurney Bay Development in Penang. Delivered for JKR, the package supports the wider public waterfront development.

The works comprised the controlled placement of approximately 150,000 m³ of sand and soil to form the reclaimed platform. The Initial Stage gallery records access preparation, sheet-pile and marine works, material inspection and on-site coordination. The Development Stage gallery shows excavation, perimeter works and earthworks before completion.

Completed on 24 December 2025, the reclaimed platform is documented in the Completed Project aerial gallery. The delivered works demonstrate TPJ Engineering’s capability in marine construction and land reclamation. Explore our project portfolio for further examples of our infrastructure delivery.

Client

JKR

Contract Sum

RM 23,700,000.00

Project Duration

8 February 2024 - 24 December 2025

Location

Gurney Bay, Penang